  • By September 25th, the excavation of the Southbound lane will be complete. 


  • Grading and the installation of the curbs will take place thereafter and should wrap up by September 30th. 


  • Installation of the road base will begin in early October and wrap up by October 11th. 


  • The installation of sidewalks, driveways, topsoil and seed is scheduled to begin October 14th and end by November 6th. 


  • The surface course of asphalt will take place November 7-11th


  • Final striping is tentatively scheduled for November 12th 


  • The cleanup and cone removal will take place sometime around November 13-15th 